Building Electrical Power Shutdown
Facility Services will continue testing the University’s primary electrical distribution system which will result in the interruption of electrical service for a period of time in each impacted building. This work is necessary to minimize a reoccurrence of the electrical power failure which occurred during December 2018. Each sectional switch will be tested to assess its current condition. Please make arrangements to work in other building locations throughout campus while this testing work is going on in your building.
Additional sectional switch testing and associated electrical power shut downs will occur during the end of the spring semester (5/18-5/22/2020). Facility Services will provide additional notifications at that time.
The testing schedule for April 9-13, 2020 by building and approximate shut down durations are as listed below:
April 9, 2020 – Thursday
- Clet Hall – 8 Hours, 7:00AM-3:30PM + or –
- Alumni Hall – 8 Hours, 7:00AM-3:30PM + or –
- Alumni Annex – 4 Hours, 7:00AM-12:00PM + or –
- Marian – 8 Hours, 7:00AM-3:30PM + or –
April 10, 2020 – Friday
- Butler – 8 Hours, 7:00AM-3:30PM + or –
- Dunleavy – 8 Hours, 7:00AM-3:30PM + or –
- Kiernan – 8 Hours, 7:00AM-3:30PM + or –
April 13, 2020 – Monday
- O’Shea – 4 Hours, 7:00AM-12:00PM + or –
- Bisgrove/ACAD – 8 Hours, 7:00AM-3:30PM + or –
- Physical Plant – 8 Hours, 7:00AM-3:30PM + or –
- Varsity Village – 8 Hours, 7:00AM-3:30PM + or –
- Timon – 8 Hours, 7:00AM-3:30PM + or –
Thank you for your cooperation while we undertake this necessary work and if you have any questions or concerns, please contact Facility Services at ext. 8430