DUNLEAVY WINDOWS / DEPAUL MASONRY / ST. VINCENT’S HALL MASONRY INVESTIGATION WORK

In Announcements, by , on July 1st, 2020

RE Kelley will be on site as early as June 18th  but no later than June 22nd, 2020 to begin the following work. They will begin with:

Dunleavy Window Replacement

SCOPE: Replace windows in the Northwest Stairwell and in Classroom 204 (area across the street from ACAD)

DURATION: 1-3 Days

Please be aware they will have lifts in the area to be able to access the needed areas

They will then move to:

DePaul Hall Masonry

SCOPE: Replace 2 masonry panels on the north end of the building (closest to Gallagher)

DURATION: 1-2 Weeks

Please be aware they will have lifts in the area to be able to access the needed areas

Once complete at DePaul they will move to:

St Vincent’s Hall Masonry Investigation

SCOPE: Remove and replace panel on Southeast End of the Building

DURATION: 1-2 Days

Please be aware they will have lifts in the area to be able to access the needed areas

This work will requiring the closing of the South Entrance (Nearest St. Vincent’s Annex) during the times work is actively going on

Please be aware of this work and the approximate scheduled days.

Note:  This scheduled work project may run through July 10th.